Meeting Date:
|
12/8/2021 - 7:00 PM
|
Category:
|
Consent Agenda Items
|
Type:
|
Action
|
Subject:
|
Approval of Bids for 2022 Facility Improvements: Capital Improvements - Door Replacements at 11 buildings and Foods Lab Renovation at Wheaton Warrenville South High School
|
Vision 2026:
|
Financial & Facilities Management 2 Continue to work to address projects identified in the Facilities Master Plan, through the dedicated budget allocation for capital facility projects per Board policies.
|
Background
|
The administration identified and prioritized several exterior door replacement projects at eleven (11) buildings and the Wheaton Warrenville South High School Foods Lab renovation. These projects are included in the capital plan and were reviewed and recommended by the Facilities Committee prior to bidding.
|
File Attachment:
|
|
Summary:
|
The bid opening was held on November 30, 2021. Fifteen (15) contractors obtained bid packets, and six (6) contractors responded. The bid package was structured into just a base bid package with several alternates. Attached is a letter from Legat Architects recommending Manusos General Contracting, Inc., as the low bidder on the base bid package, in the amount of $1,044,110.
|
Funding:
|
O & M Capital Renewal Fund and Capital Projects Fund
|
Board Policy
:
|
|
Recommendation:
|
It is recommended that the Board of Education award the base bid for door replacements at 11 buildings and the Foods Lab renovation at Wheaton Warrenville South High School to Manusos General Contracting, Inc., in the amount of $1,044,110.
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
Brian O'Keeffe - Asst Superintendent Business Services
|
|
Signed By:
|
|
Jeff Schuler - Superintendent
|
|
|
|
Vote Results:
|
Original Motion | Member Susan Booton Moved, Member Brad Paulsen seconded to approve the Original motion 'It is recommended that the Board of Education award the base bid for door replacements at 11 buildings and the Foods Lab renovation at Wheaton Warrenville South High School to Manusos General Contracting, Inc., in the amount of $1,044,110.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 7 Nay: 0. | The motion Carried 7 - 0 | | | Brad Paulsen | Yes | Chris Crabtree | Yes | Rob Hanlon | Yes | Susan Booton | Yes | Dave Long | Yes | Mary Yeboah | Yes | Angela Blatner | Yes | |
|
|
|
|
|
|