Subject:
|
Approval of DoIT Network Refresh
|
Vision 2026:
|
Financial & Facilities Management 3 Monitor and update the annual Master Technology Plan.
|
Background
|
DoIT seeks to establish a predictable life cycle replacement schedule of all network equipment.
|
File Attachment:
|
|
Summary:
|
DoIT is seeking a $1.75 million dollar investment to upgrade core components of its network infrastructure.
|
Funding:
|
Total project cost - $1,753,972.20 ERATE reimbursement - $689,961.10 ESSER II & ARP ESSER - $1,000,000 Department Budget - $64,011.10
|
Board Policy
:
|
4:60 Purchases and Contracts 6:235 Access to Electronic Networks
|
Recommendation:
|
It is recommended that the Board approve the network refresh project so as to allow the district to establish a predictable refresh cycle moving forward and avoid any disruption to core services.
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
Jason Spencer - Exec Director of Innovation and Technology
|
|
Signed By:
|
|
Jeff Schuler - Superintendent
|
|
|
|
Vote Results:
|
Original Motion | Member Rob Hanlon Moved, Member Susan Booton seconded to approve the Original motion 'It is recommended that the Board approve the network refresh project so as to allow the district to establish a predictable refresh cycle moving forward and avoid any disruption to core services.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 7 Nay: 0. | The motion Carried 7 - 0 | | | Brad Paulsen | Yes | Chris Crabtree | Yes | Rob Hanlon | Yes | Susan Booton | Yes | Dave Long | Yes | Mary Yeboah | Yes | Angela Blatner | Yes | |
|
|
|
|
|
|